Felsenburg House, designed by the swiss practice Sara Gelibter Architecte, involves the renovation and vertical expansion of an existing building located in Biel/Bienne, Switzerland.

Adopting an approach of economy of means, the project preserves and reuses available resources; it also benefits from the active participation of the owners—through ongoing dialogue and collaboration—who were directly involved in various phases of the construction.

The intervention by Sara Gelibter Architecte adds a new floor atop the existing structure, creating space for two additional rooms for the owners' use. Furthermore, the facade facing the railway tracks is enclosed to minimize noise exposure, while the opposite side opens up toward the Alpine landscape, establishing a direct connection with the natural environment.

The extension is constructed using a prefabricated timber framework. To achieve acoustic insulation, a lightweight build, and ease of assembly, the design employs an exterior cladding made of fiber cement—composed of recycled cement and wood fibers—and incorporates materials salvaged from the original building.

Felsenburg House by Sara Gelibter Architecte. Photograph by Cyril Käppeli.

Felsenburg House by Sara Gelibter Architecte. Photograph by Cyril Käppeli.

Project description by Sara Gelibter Architecte

Felsenburg House is a project by Sara Gelibter Architecte involving the renovation and vertical extension of an existing building for an artist couple. The clients purchased the property in 2020. During the initial site visit, several critical issues emerged, which later proved pivotal in the development of the project.

Only after the purchase did the owners discover that the roof was structurally unsound. What had initially been conceived as a minor interior refurbishment evolved into a complex renovation, including the addition of an entirely new floor.

Felsenburg House by Sara Gelibter Architecte. Photograph by Cyril Käppeli.

The core idea of the project centres on the intersection of factors like the existing building, budget constraints, and the client’s desire to experiment with low environmental impact solutions. The building’s origins lie in the local wine industry, dating back to when Biel was still a rural village. The first nucleus was essentially a simple shed, later converted into a building serving the metal galvanisation industry. Although precise data is lacking, the railway line was likely constructed during this phase: the trapezoidal shape of the extension appears to have been dictated by the presence of the tracks. Originally, the building stood in a context free of railways; in the 1920s and 1930s, and then, with the arrival of the train, was expanded laterally and vertically. Subsequently, a separate volume was added, used for industrial production for about fifty years, until its transformation into a youth hostel in 1968.

Felsenburg House by Sara Gelibter Architecte. Photograph by Cyril Käppeli.

From that point onward, the building underwent a series of fragmented and inconsistent interventions that progressively compromised its structure: it was subdivided into small rooms, and the rhythm of the windows was altered, and in the 1980s, it suffered severe damage when it was converted into family housing. At that time, the ceiling height was raised to 2.40 metres to make the top floor habitable, and the tension rods that ensured the structural integrity of the spans were cut. The structural damage to the roof went unnoticed for over forty years, which is why the clients were unaware of it when purchasing the property.

From these critical issues emerged an opportunity to develop a radically different project. An analysis of the current regulatory framework identified the possibility of adding a floor to the building, a feature that shaped the intervention. The need to reconstruct the now precarious roof provided the chance not simply to replicate the existing form, but to imagine a completely new solution: a sort of ‘house on top of a house’, increasing the total volume and floor area and allowing for the addition of two new rooms to accommodate the clients’ activities. This transformation, clearly visible in the architectural profile of the building, gave the project a distinctive character, making it a true recognisable landmark within the village.

Felsenburg House by Sara Gelibter Architecte. Photograph by Cyril Käppeli.

The construction method adopted, however, was dictated by practical logic: using prefabricated wood allowed the new structure to be assembled in a single day thanks to the combined use of a helicopter and on-site carpentry work. Regarding the exterior, design choices were strongly influenced by the need to protect the building from train noise. Fibre cement, made from recycled cement and wood fibres, was used because of its high sound inertia, low specific weight, and ease of installation. In addition to the use of insulating materials, the treatment of openings was also crucial: all existing windows on the railway side were closed, while the building fully opens on the other side towards the Alps.

A unique aspect of this project was the relationship established with the owners, who were open to unconventional solutions and actively participated in the design process, proposing ideas and carrying out a significant portion of the work. They took full responsibility for the ground floor, completing the flooring, painting, drywall, plasterwork, and furniture. The clients’ family has always maintained a strong connection to the construction world: the husband’s father worked in set design and lighting, while the wife’s brother is an electrician; both contributed to various aspects of the project.

Felsenburg House by Sara Gelibter Architecte. Photograph by Cyril Käppeli.

For the additional floor, every effort was made to reuse materials whenever possible: for example, elements from the existing kitchen were salvaged and integrated into the new living space. A temporary protective structure was necessary during the roof opening, and all materials used for this structure were later reused for internal insulation. Wooden, instead of metal structures, were chosen to support the drywall. The recovered wood was also used to build an external pergola and make furniture. Finally, the inside stairs were salvaged from a theatre dismantled by the husband’s father, which coincidentally matched the building’s floor-to-floor height, creating a symbolic detail. Other prefabricated elements were transported and installed on the day of the helicopter lift.

A Word from the Architect
What I find most beautiful about this project is that it allowed two people, who are not architects, to discover a sensibility they likely didn’t even know they had. They had never imagined building their own home, yet seeing their natural inclination toward this kind of approach, I supported them in expressing their talent, almost as if they had become architects themselves. Today, my greatest satisfaction is seeing them happy with the result and feeling deeply connected to the project.

Construction process. Felsenburg House by Sara Gelibter Architecte.

We met organically: a few years ago, I used to take my children to an association called “Mamma di giorno,” and it was there that I met the director, who is the mother of one of the clients. Over time, we became close friends. The clients shared their enthusiasm for every choice because every decision was shared, discussed, and explained. I learned a lot from them as an architect. I realised that, especially in private projects, the best results come from sharing and collaboration. I no longer think of them simply as ‘clients’, because over the years, they have become people with whom I continue to share an affinity and vision. After four years of ongoing dialogue, the most beautiful thing has been seeing them feel like they were a part of everything that happened, whether positive or challenging. Solutions were never imposed; instead, they sprang up and evolved naturally.

When I first entered their new place, I thought, ‘This is exactly how I would have done it.’ Not because it looks like my own home, but because of the authenticity with which it came to life. Today, that house is a little bit mine as well.

More information

Label
Architects
Text

Sara Gelibter Architecte GmbH. Lead architect.- Sara Gelibter.

+ + copy Created with Sketch.
- + copy Created with Sketch.
Label
Collaborators
Text

Masonry.- R. Mantuano Sàrl, Peseux.
Carpentry.- J.K-Charpente (@jeremy_kocher.ch), Brügg.
Sanitary installations.- Despont, Biel/Bienne.
Structural engineering.- Schmid und Pletscher AG, Nidau.
Flooring.- Posarte, Kerzers.
Painting and plasterwork.- Giampani, Biel/Bienne.
Roofing and sheet metal work.- Major Toiture, Biel/Bienne.
Scaffolding.- Fasel, Neuchâtel.

+ + copy Created with Sketch.
- + copy Created with Sketch.
Label
Area
Text

280 sqm.

+ + copy Created with Sketch.
- + copy Created with Sketch.
Label
Dates
Text

2020 - 2024.

+ + copy Created with Sketch.
- + copy Created with Sketch.
Label
Location
Text

Biel/Bienne, Switzerland.

+ + copy Created with Sketch.
- + copy Created with Sketch.
Label
Budget
Text

Roof extension.- €650,000.
Self-construction.- €217,000.

+ + copy Created with Sketch.
- + copy Created with Sketch.
Label
Photography
+ + copy Created with Sketch.
- + copy Created with Sketch.

Sara Gelibter Architecte is an architectural practice founded by Sara Gelibter in 2019, based in Biel/Bienne, Switzerland, and incorporated as Sara Gelibter Architecte GmbH in 2024. Her architectural education, developed across Italy, Valencia and Copenhagen, has shaped an open-minded approach to different cultural and architectural contexts. The studio currently consists of a five-person team and works on projects of varying scales, from small renovations and extensions to public buildings.

Its practice is rooted in an understanding of architecture that places people at its centre, with listening, dialogue and mutual trust forming the foundations of the design process. The active involvement of clients and collaboration with other architectural practices are integral to its methodology, approaching each project as a collective endeavour capable of bringing together different needs, aspirations and knowledge.

An economy of means defines the studio’s material and construction approach: making use of existing structures, reclaiming materials and developing precise interventions that create new spatial qualities with limited resources. This philosophy translates into an architecture that prioritises what is essential, explores simple construction solutions and recognises the value of what already exists. In recent years, the studio has won three architectural competitions for educational and childcare buildings in Brig-Glis, Courroux and Bellmund, in collaboration with other practices.

Read more
Published on: November 27, 2026
Cite:
metalocus, CAMILA DOYLET
"Second life. Felsenburg House by Sara Gelibter Architecte" METALOCUS. Accessed
<https://www.metalocus.es/en/news/second-life-felsenburg-house-sara-gelibter-architecte> ISSN 1139-6415
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...
Loading content ...